Error "Capital Distribution Cannot Exceed Project Capital Budget" When Attempting to Lock a Project's Cost Sheet Budget Distribution (Doc ID 2891406.1)

Last updated on AUGUST 24, 2022

Applies to:

Primavera Unifier Cloud Service - Version 22.7 to 22.8 [Release 22.7 to 22.8]
Information in this document applies to any platform.

Symptoms

When attempting to lock the budget distribution for a project cost sheet, the following alert message displays.

Alert

Capital Distribution cannot exceed Project Capital Budget

 

The issue can be reproduced at will using the following steps:

  1. In Unifier, navigate to the desired Project and open the Cost Sheet.
  2. Change the WBS Item for a desired WBS Code.
  3. The Budget Distribution amounts are correctly displayed and totaled.
  4. Attempts to lock the budget distribution.
  5. The reported alert occurs even though the amounts are the same.
  6. Reduce the budget distribution by 1 cent.
  7. The user is now able to lock the budget distribution.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.