Symptoms

ACTUAL BEHAVIOR

Calendar being associated to a new activity in a project, if No calendar is set in project is NOT associating to the Workspace Default Workspace

EXPECTED BEHAVIOR

Assumed behavior expectation: workspace default calendar will pass down to project activity calendar, if there is no default for project calendar set.

STEPS To REPRODUCE

  1. Access OPC
  2. Navigate to Project > Schedule > Activities
  3. Open Calendar Column
  4. Create NEW activity
  5. View and Record Calendars associated
  6. Navigate to Projects Summary & Settings > Dictionaries > Calendars
  7. For the affected Project, No "Calendars" are listed for Project
  8. Navigate to the Workspace (the project is assigned) Summary & Settings > Dictionaries > Calendars
  9. Notice the Default
  10. Compare the New Activity Calendar to the Workspace Default Calendar Dictionary

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.