My Oracle Support Banner

PRC:PO: Purchase Orders Created from RFQ Award Are Missing Link with Requisition (Doc ID 2897906.1)

Last updated on SEPTEMBER 22, 2022

Applies to:

Oracle Fusion Purchasing Cloud Service - Version 11.13.22.04.0 and later
Oracle Fusion Purchasing - Version 11.1.9.2.0 and later
Information in this document applies to any platform.

Symptoms

When creating Purchase Order (PO) from RFQ award and is fully allocated to the requisition linked with the RFQ but once PO is created, it is not linked to the requisition.

STEPS
-----------------------
The issue is not reproducible, but it happened following the below steps:
1. PR linked to RFQ
2. Complete the Award process
3. Created the Purchasing Document
4. Once the PO was created, the requisition number is blank

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.