After Importing Microsoft Project XML, Remaining Durations, % Complete, Actual Durations, Finish Date Are Not As Expected
(Doc ID 2901025.1)
Last updated on DECEMBER 07, 2022
Applies to:
Oracle Primavera Cloud Service - Version 22.1 and laterPrimavera P6 Enterprise Project Portfolio Management Cloud Service - Version 18.1 and later
Primavera P6 Enterprise Project Portfolio Management - Version 18.8 and later
Primavera P6 Professional Project Management - Version 18.8 and later
Information in this document applies to any platform.
Symptoms
After Importing Microsoft Project (MSP) XML file, some Remaining Durations, % Complete, Actual Durations and Finish Date Are Not As Expectedd
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |