Budget Amount Incorrect On Award Overview
(Doc ID 2906068.1)
Last updated on AUGUST 08, 2024
Applies to:
Oracle Fusion Grants Management Cloud Service - Version 11.13.22.04.0 and laterInformation in this document applies to any platform.
Symptoms
On : 11.13.22.04.0 version, Award Overview
ACTUAL BEHAVIOR
Budget amount incorrect on Award overview
EXPECTED BEHAVIOR
Budget amount correct on Award overview
STEPS
The issue can be reproduced at will with the following steps:
1. Manage Awards: Budget amount incorrect on Award overview , for example:
Award : P_NR with project : P_NR has project budget $659,305.00
But the Award Overview is showing budget doubled 1,318,610.00 .
2. Manage project budget version: Cost budget: $659,305.00
Cause