Symptoms

When adding an EPS column or a filter for EPS to a report, the costs are doubling.

For example, when adding a filter for EPS level name, the Actual Cost shows double the value. Removing the EPS filter shows the correct cost.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a new analysis based on the Project History subject area
2. Add the columns Project Id, Project Name and Actual Total Cost
3. Run the report and see the costs are correct
4. Add a filter on EPS Name
5. Run the report and see the costs are doubling for each project

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.