My Oracle Support Banner

Guide to OTM/GTM Migration to OCI GEN2 (Doc ID 2918678.1)

Last updated on JULY 31, 2023

Applies to:

Oracle Transportation Management Cloud Service - Version 23.2 and later
Information in this document applies to any platform.

Goal

To provide you with a high-level view of the migration and steps involved to move your environments from Oracle Public Cloud Infrastructure (OPC) Generation 1 (Gen1) to Oracle Cloud Infrastructure (OCI) Generation 2 (Gen2).

This migration will provide:

Read more about Second Generation Oracle Cloud

 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
 Migration Process
 Pre-Migration Key Activities
 Step-by-Step Customer Guide
 1. Confirm Correct Gen2 Cloud Account Welcome Email Recipient (Deadline - Immediate)
 2. Assess P2T and Weekly Patch Needs and Submit Requests (Deadline - 6 weeks before Test cutover)
 3. Confirm All End Users Login Using Direct Environment URL (Deadline - 4 weeks before Test cutover)
 4. Review Available Documentation (Deadline - ASAP)
 5. Assess Migration Impact on Integrations (Deadline - Immediate)
 6. Assess Work to Comply with New Gen2 Email From Address (Deadline - Test cutover) 
 7. Confirm Access to New Gen2 My Services Cloud Account (Deadline - 3 weeks before Test cutover)
 8. Begin Federated SSO, VPN, and GoldenGate Set Up, as Necessary (Deadline - As soon as you have access to your new Gen2 Cloud Account)
 9. Manage My Services Cloud Account SSO Users (Deadline - Tuesday before Test cutover)
 10. Complete Migration and Quarterly Update Validation Testing (Deadline - Test cutover)
 Issues, Exception Requests, Etc.
  
References