ACTUAL BEHAVIOR

A Resource's (R1) assignment in My Activity is showing as 'In Progress' and has a Start Date in the past, even though it has not yet started.  They are unable to edit the Start date to something in the future that reflects when they actually plan to work on the activity.

This behavior only occurs when another Resource (R2) starts their work before the R1 and the Planned Start date for R1 is before the Planned Start date R2.  If the Planned Start dates are reversed (so that R2's date is before R1's date), and R2 starts their assignment first, R1's assignment remains as 'Not Started'.

EXPECTED BEHAVIOR

Each Resource's assignment on an activity is expected to be independent, so that when one resource makes an update to an activity it would not change the status and Start date for other Resource assignments.

 

The issue can be reproduced at will using the following steps:

  1. Create an activity with multiple resources assigned to it.
  2. Set the Planned Start date for R1 to a date earlier than for R2.
  3. R2 starts the assignment before R1 has started on it.
  4. Observe the reported behavior.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.