My Oracle Support Banner

When a Change Is Made to the Quantity DE in the Business Process (BP) Line Item Table, the Changes Are Not Updating in the Payment SOV (Doc ID 2931725.1)

Last updated on MARCH 08, 2023

Applies to:

Primavera Unifier Cloud Service - Version 23.2 and later
Primavera Unifier - Version 9.7 and later
Information in this document applies to any platform.

Symptoms

When a Change Commit is created to update the value of the Quantity Data Element (DE) in a line item, once the Change Commit record is approved, and a new Payment BP record is created, the change is not reflected in the respective line item's Quantity DE.

However, the Schedule of Values (SOV) shows the correct updated value.

EXPECTED BEHAVIOR:

When the customer make changes to Quantity DE, it should also update in the Payment SOV.

STEPS TO REPRODUCE:

  1. Create a Change Commit BP record against a Base Commit record that has unit price line items.
  2. In the Change Commit, add a line item updating the quantity for one of the Base Commit line items.
  3. Approve the Change Commit BP record.
  4. Create a new Payment BP record and select the same Base Commit record.
  5. Click on the line item tab and add in the line items.
  6. See that the payment grid in the BP record shows the old value in the Quantity DE.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.