Activities Are Not Being Picked Up As Critical Activities When Running Schedule By Setting 'Total Float Equal or Less Than' Value
(Doc ID 2933600.1)
Last updated on MARCH 09, 2023
Applies to:
Oracle Primavera Cloud Service - Version N/A to N/A [Release NA]Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
When setting the schedule critical setting to "Total Float Equal or Less Than" = n, activities with Total Float value less or equal to nd are not picked up as critical.
But if set this value to 'nd' instead of 'n', the expected activities are picked up as critical. If now, users click Schedule again, the default "Total Float Equal or Less Than" is auto changes to n*8 instead of nd.
The issue can be reproduced at will with the following steps:
- Log into OPC.
- Navigate to project schedule page.
- Click on Schedule button->(Settings tab) "Total Float Equal or Less Than" = n->Click Schedule Now.
- Found the activities with Total float equal or less than 5d are not picked up as critical.
- Click on Schedule button->(Settings tab) "Total Float Equal or Less Than" = nd ->Click Schedule Now.
- Found the activities with Total float equal or less than 5d are critical now.
Changes
Cause