Gates Refresh Does not Advance to Next Phase
(Doc ID 2949742.1)
Last updated on MAY 18, 2023
Applies to:
Primavera Unifier Cloud Service - Version 23.4 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
When attempting to advance a Project Gate to the next phase by editing the phase and marking all Conditions as Complete and checking Ignore Condition* and then saving, the phase does not advance when refresh is selected, it stays at the current gate.
EXPECTED BEHAVIOR
-----------------------
If all conditions of a phase are met, it should be able to advance to the next phase.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
- Navigate to a Project that contains a Gate with more than one phase and is not in the final phase.
- Navigate to the Gates and select the current phase > Edit.
- Select Complete and Ignore Condition for all conditions of the phase > Apply > Ok.
- Select Refresh to validate the gate Conditions Manually.
- Note that the Gate does not advance in phase.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |