ACTUAL BEHAVIOR

In P6 Web, the summarization in Portfolio Scorecards is not working for % complete fields on higher levels than project level such as Totals and Subtotals.

Affected Fields:

  


EXPECTED BEHAVIOR

Totals for % Complete fields should be visible in summary bands.



STEPS TO REPRODUCE

The issue can be reproduced at will with the following steps:

  1. Open a scorecard with the following columns:
  2. Go to Portfolios.
  3. Login to P6 Web.
    • Schedule % Complete
    • Performance % Complete
    • Units % Complete
    • Performance % Complete - Labor Units
  4. Notice that they are either blank or at 0% though there is data at the project level.

 

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.