Goal
On : 22C version, WAM Work Management
ACTUAL BEHAVIOR
---------------
WACS-OFS Work Skill (Craft) is not populated in Timesheet (Resource Usage plugin)
Work Skill (Craft) is not populated in Timesheet (Resource Usage plugin).
Please see the attachment.
Steps to reproduce:
1. Work Skills are assigned to the resource
2. Assign an activity to the resource
3. Start and lock the activity
4. Navigate to the Resource Usage plugin
5. Click add timesheet
6. Craft is expected to be automatically populated. However, it appears to be blank
Solution