Fusion Absence Management: System is not considering the correct absence duration when 0.5 days of Public Holiday present for the same absence date
(Doc ID 3003974.1)
Last updated on FEBRUARY 15, 2024
Applies to:
Oracle Fusion Absence Management Cloud Service - Version 11.13.23.07.0 and laterInformation in this document applies to any platform.
Goal
System is not considering the correct absence duration when 0.5 days of Public Holiday present for the same absence date.
Example:
Employee have a work schedule of 9 hours from 8 AM to 5 PM.
Create a calendar event (Public Holiday) for any one day, from 8 AM to 12:30 PM. Assign this calendar event to the same work schedule.
Now, when you check the employee calendar, we can see 4.5 hours of public holiday (from 8 AM to 12:30 PM) and remaining 4.5 hours of a scheduled work day (12:30 PM to 5 PM).
Try to record an absence for the same date. Absence Start Time and End Time will be displayed correctly (Start Time as 12:30 PM and End Time as 5 PM).
But the duration is considered as 1 Days (not 0.5 Days).
Solution