Error "PRM-003015036" When Importing Project File To Update Existing Project
(Doc ID 3005956.1)
Last updated on MARCH 08, 2024
Applies to:
Oracle Primavera Cloud Service - Version 24.1 to 24.1 [Release 24.1]Information in this document applies to any platform.
Symptoms
On : 24.1 version, Cloud: Schedule, Progress and Tasks
When attempting to import a P6 project xml/xer to update the existing project in Oracle Primavera Cloud (OPC), the following error occurs.
If import the P6 xml/xer as a New project, it can be imported successfully.
ERROR
Import failed due to a business rules conflict. You cannot enter a remaining finish date for a resource assignment for a completed activity. (PRM-003015036).
The issue can be reproduced at will with the following steps:
- Log into OPC.
- View All projects and select the target workspace->Action ->Import P6 xml/xer.
- Select the P6 xml/xer with Update option.
- Import failed with above error.
Changes
Cause