My Oracle Support Banner

Suggested Start Date Not Honoring Preprocessing Lead Time In Source Org For Transfer Orders In RP (Doc ID 3017414.1)

Last updated on APRIL 17, 2024

Applies to:

Oracle Fusion Planning Central Cloud Service - Version 11.13.24.01.0 and later
Information in this document applies to any platform.

Symptoms

On : 11.13.24.01.0 version, Release Orders

ACTUAL BEHAVIOR
---------------
Suggested Start Date is not honoring preprocessing lead time in source org for transfer orders in Replenishment Planning
 

EXPECTED BEHAVIOR
-----------------------
Show the correct suggested order date on planned orders

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Supply Chain Planning > Replenishment Planning
2.Click on Run to run the Replenishment Plan
3. Validate the dates for the generated output.
4. Plan is making wrong recommendations with wrong calculation dates on internal Requisitions.



Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.