Cannot Update Percent Complete On Manage Tasks (Doc ID 3048034.1)

Last updated on SEPTEMBER 24, 2024

Applies to:

Oracle Fusion Project Foundation Cloud Service - Version 11.13.24.04.0 and later
Information in this document applies to any platform.

Symptoms

On : Manage Project Tasks

ACTUAL BEHAVIOR

Cannot Update Percent Complete on Manage Tasks

EXPECTED BEHAVIOR

Able to Update Percent Complete on Manage Tasks

STEPS

The issue can be reproduced at will with the following steps:
1. Since 24B upgrade, users cannot update "Percent Complete" in My Tasks page.
2. This is not happening for all tasks...just some tasks. The expected functionality is that users can see all tasks assigned to them on "My tasks" and update them to complete. However since 24B upgrade users are not able to do this for all tasks. Some tasks do not show the option to update. We have no work-around.



Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.