End Date Costs Do Not Change after Updating Start Date in Portfolio Sheet
(Doc ID 3064009.1)
Last updated on DECEMBER 19, 2024
Applies to:
Primavera Unifier Cloud Service - Version 24.8 to 24.11 [Release 24.8 to 24.11]Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
When modifying the project dates in the Capital Planning functionality, the cost distribution is only shifted for the period where the years are broken down in months. For the rest of the period, the distribution stays the same as it was before the dates were changed.
EXPECTED BEHAVIOR
-----------------------
The cost distribution should reflect the Project End Date change.
Cause