OPC Does Not Import Baseline Interproject Relationships
(Doc ID 3077679.1)
Last updated on MARCH 19, 2025
Applies to:
Oracle Primavera Cloud Service - Version 25.2 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
When trying to import projects that have interproject relationships between them, both between the project and also between the baselines, OPC maintains the relationships between projects in the current schedule but it deletes the relationships between the baselines.
EXPECTED BEHAVIOR
-----------------------
Baseline interproject relationships should also be imported.
Changes
Cause