R12 NOT ABLE TO TRANSFER ANY TRANSACTIONS FROM PROJECT ACCOUNTING MODULE TO GENERAL LEDGER (Doc ID 1052452.1)

Last updated on AUGUST 01, 2016

Applies to:

Oracle Project Costing - Version 12.0.6 and later
Information in this document applies to any platform.
*** Checked for Relevance 17-Oct-2014 ***


Goal

New Total Burdened Costs events for labor transaction are created but they will not interface to GL. Users submit the interface streamline process for Streamline Option: XB Interface Total Burdened Costs to GL but the events are not picked up and transferred to GL.


How do we get these total burdened costs to interface to GL?