FORWARD SCHEDULING FROM THE DISCRETE JOB FORM BEHAVING INCORRECTLY WITH MULT OPERATIONS (Doc ID 1071183.1)

Last updated on MARCH 09, 2016

Applies to:

Oracle Work in Process - Version 12.1.1 to 12.1.3 [Release 12.1]
Information in this document applies to any platform.

Symptoms

WIP jobs seem to be scheduling incorrectly.
How to replicate:

When !E100 stands alone in the routing, it starts on 2/1 and ends on 2/12. And that is correct. When I add 2M100 the routing, making it the second operation, the first operation (1E100) gets scheduled correctly 2/1 - 2/12. But the second operation (2M100) gets scheduled 2/12 - 2/15 and I have no explanation for it. It should be 2/12 - 2/26 according to what I've seen in the past.