R11 R12 PAXACRPT PRC: Refresh Project Summary Amounts Performance Is Slow And Does Not Show Commitment Costs in Project Status Inquiry (PSI)
(Doc ID 1075453.1)
Last updated on SEPTEMBER 05, 2024
Applies to:
Oracle Project Planning and Control - Version 11.5.10.2 and laterInformation in this document applies to any platform.
Symptoms
Zero commitment costs display in Project Status Inquiry (PSI) after running the PRC: Refresh Project Summary Amount with no parameters entered.
Expecting commitment costs to display in PSI.
Along with this, experiencing performance issues which could be a cause on why the commitments are not appearing in PSI.
Changes
Upgraded from 11.5.10 to 11.5.10.2 (CU2) with M RUP 4 which is causing poor performance in both PRC: Refresh (and Update) Project Summary Amounts. Before the upgrade, there were no performance issues with the PRC: Update Project Summary Amounts. It is unknown if the PRC: Refresh Project Summary Amounts was experiencing performance issues before the upgrade as this is a process that is not normally run.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |