R12 11i Rejected Requisition Still Show in PSI Commitments

(Doc ID 1109104.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Planning and Control - Version 11.5.10.2 and later
Information in this document applies to any platform.

Goal

Question 1:

Rejected requisitions are still shown in the PSI commitments and transactions, is that correct?

Navigation
            Create requisition
            1 approver accepted
            2 approver rejected
                        - Req status Rejected
                        - Requisition still updated in PSI commitments.


Question 2:

Is the requisition 'deleted' from commitment when the requisition is closed?


Solution