Goal

How To Create a GL Transfer schedule to accomplish the following:

Start Date: 01-APR-2010
Post Thru Date: 02-APR-2010
GL Posted Date: 02-APR-2010

The schedule needs to keep the Start Date static for the month and change the Post Thru and GL Posted Dates incrementally

first run:
Start Date: 01-APR-2010
Post Thru Date: 03-APR-2010
GL Posted Date: 03-APR-2010

second spawned run:
Start Date: 01-APR-2010
Post Thru Date: 04-APR-2010
GL Posted Date: 04-APR-2010

third spawned run:
Start Date: 01-APR-2010
Post Thru Date: 05-APR-2010
GL Posted Date: 05-APR-2010

.......continue to create spawned run until the date reaches the end of the period

Then when the period changes to May, set up a new schedule to start at:

Start Date: 01-MAY-2010
Post Thru Date: 01-MAY-2010
GL Posted Date: 01-MAY-2010

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms