[Datafix] Unable to See Material Requirements for Work Orders if Operations with Sequence 1 are Associated with Maintenance Routes

(Doc ID 1121779.1)

Last updated on JANUARY 02, 2016

Applies to:

Oracle Complex Maintenance, Repair, & Overhaul - Version 12.1 and later
Information in this document applies to any platform.
***Checked for relevance on 03-Jan-2016***

Symptoms

Find that Material Requirements for some Routes are not visible on the Workorder.


EXPECTED BEHAVIOR
Expect to be able to see the Material Requirements defined in the Route on the Workorder.


STEPS
(R) Complex MRO responsibility
(N) Engineering > Route management > Routes
1. Create Route with Operation sequence as "1"- Add Material Requirements (MR)
2. Add Route to an MR.
3. Create a Visit - Add the MR
4. Release the Workorders
5. Check Workorders > Materials
6. Material Requirements are not visible on the Workorder.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms