Symptoms

Reports display the wrong cost after WIP Assembly Return transactions are processed.


The issue can be reproduced with the following steps:

1. Create WIP discrete job without a Bill of Materials and Standard Routing
2. Release job
3. Add new material in material requirements with Supply type : Assembly Pull>Save
4. Create Assembly Completion
5. Create Assembly Return
6. Stop the Cost Manager and modify the material requirement.
    Reset the material added in step 3 to 0 and add a new one
7. Start Cost Manager
8. Review distribution for the assembly return and WIP return

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms