Can Schedule Ship Date Be System Changed To Earlier Than Today's Date, Order Date Type=Arrival

(Doc ID 1131168.1)

Last updated on SEPTEMBER 20, 2017

Applies to:

Oracle Order Management - Version 12.1.1 to 12.1.3 [Release 12.1]
Information in this document applies to any platform.
***Checked for relevance on 13-AUG-2012***

Goal

If you check the 'Override ATP' box, you are able to schedule a line (with Order Date Type = Arrival) - and the Schedule Ship Date was update to a date prior to today's date.
1. Should the SSD calculate to a date prior to system date (today's date) when 'Override ATP' box is checked?
2. Is this a bug?

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms