Symptoms
When attempting to schedule an already split task, the following error occurs.
ERROR
-----------------------
This update operation is not allowed for the task &TASK_NUMBER, because it is either a parent or child task or a task longer than shift.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create task bigger than shift
2. Schedule task (task will be split)
3. Attempt to update any task, (child or parent).
Changes
Cause