Absence Duration Not Recalculated After Formula Changed (Doc ID 1355372.1)

Last updated on MARCH 03, 2017

Applies to:

Oracle Human Resources - Version 12.1.3 and later
Information in this document applies to any platform.

Goal


An absence request is submitted and between that and the time when that request is approved, the BG_ABSENCE_DURATION formula is changed such that the duration of that absence would have been calculated to a different amount.
When approved, the old duration value is committed and not the new value.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create an absence request using self servcie and submit for approval
2. change the BG_ABSENCE_DURATION fast formula, in such a way that the duration of the leave created in step 1 changes
3. approve the absence created in step 1
4. the absence is committed to database but note that the absence duration is not as per the change in the BG_ABSENCE_DURATION fast formula


Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms