Requistions/Purchase Orders Links Disappear From Work Orders Due to WIP_RESOURCE_SEQ_NUM Being NULL (Doc ID 1356688.1)

Last updated on JANUARY 07, 2016

Applies to:

Oracle Enterprise Asset Management - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version,

After receiving the purchase order for a direct item which is needed as a material requirement on a work order, the direct item is missing (disappears) from the work order material requirements.

Expect to see the material even after the purchase order was received.

The issue can be reproduced at will with the following steps:
1. Create work order, add direct item and release work order.
2. Create purchase order and receive it.
3. Observe the material not showing in the material requirements (form or self service)

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms