MSCAPO: WICMLP: Auto-release planned order fails to create WIP jobs. WIP Mass Load Output shows possible cause as " Routing was changed between collections to planning server and the release" (Doc ID 1361667.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 11.5.10.2 to 11.5.10.2 [Release 11.5]
Oracle Work in Process - Version 11.5.10.2 to 11.5.10.2 [Release 11.5]
Information in this document applies to any platform.

Symptoms



When attempting to do an Auto Release the following error occurs.

ERROR
-----------------------

The output file of the WIP Mass Load shows the following:

479198 : System cannot change/delete the following material requirement because the requested job/operation/inventory_item_id_old combo does not exist:
job (job_name): 367735
job id (wip_entity_id): 385411
operation (operation_seq_num): 10
material requirement item: 4138
item id (inventory_item_id_old): 1032199


Possible causes:
- Routing was changed between collections to planning server and the release.

STEPS TO REPRODUCE THE ISSUE:
----------------------------------------------------
1. Set up the BOM, Routing , Alternate BOM and Alternate Routing for the item.
2. Run the data collections.
3. Ensure that you create a scenario where the plan recommends the use of either alternate BOM, Alternate Routing or Both.
4. The auto-release planned orders is spawned automatically when the plan is run.
5. See that the creation of the WIP job fails with the above error.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms