PAXBUEBU Error When Baseline A Project Cost Budget - PA_FV_BUDGET_INT_FAILED - Budget baseline failed due to budget interface failure. (Doc ID 1391768.1)

Last updated on MARCH 14, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.
***Checked for relevance on 22-Dec-2014***

Symptoms


On : 12.1.3 version, Budgeting & Forecasting

ACTUAL BEHAVIOR
---------------
Encountering following error when trying to baseline a project budget from PAXBUEBU:
Budget baseline failed due to budget interface failure.
(REJECTION REASON=).
This is a fresh install of 12.1.3. Not using the budget workflow extension.

EXPECTED BEHAVIOR
---------------------------
Budget should be baselined without issues

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
Using the Project Implementation Super user responsibility
Navigate to Budgets
Find the project to be baselined using the Approved Cost Budget
Click on the Find Draft button
Click Submit button
Click Baseline button
The budget is in status of In Process and then is in the status of Rejected.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot baseline budget.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms