Symptoms


On : 11.5.10 version, MRP Runs

Find that some Blanket Purchase orders (POs) are not available in the MRP result (MRP material activity form) while they are in mtl_supply (can be seen in Supply/demand details form)

EXPECTED BEHAVIOR
-----------------------
Expect BPOs/PO seen in supply/demand screen to be also available in MRP material activity form
To be noted is that same issue is seen in MPS material activity form (PSACTDB1)

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. check with MRP material activity form for item PR2001B12-A4002
Two BPOs,  #4908(98) and #4908(107) in november
2. Check supply/demand form for same item PR2001B12-A4002 warehouse (Inventory Org) G33
3. While checking in Supply Material form:
Same two POs can be seen but also PO # 4911 twice (probably two lines) :
23-JUL-2009 : qty 120

So one misses The releases of PO#4911 in OPM MRP form

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References

This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.