PAAPIMPB: PRC: Interface Supplier Cost Process Ends with the Rejection Reason "Functional and transaction currency costs must be equal".
(Doc ID 1433367.1)
Last updated on DECEMBER 09, 2024
Applies to:
Oracle Project Costing - Version 12.1.1 and laterInformation in this document applies to any platform.
ConcurrentProgram:PAAPIMP_SI - PRC: Interface Supplier Costs
Symptoms
The process PRC: Interface Supplier Costs completes with exception
"Functional and transaction currency costs must be equal"
for PO price receipt adjustments. The output file for the process shows the transaction currency as CAD , the PO header shows the currency as USD, rcv_transactions shows the currency as CAD and rcv_receiving_sub_ledger shows the currency USD for the problem lines. Lines that successfully interface have a currency of CAD in rcv_receiving_sub_ledger.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|