Incorrect Variances are reported for Co-products on Batches when using Standard Costing.

(Doc ID 1448590.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Process Manufacturing Financials - Version 12.1.3 and later
Information in this document applies to any platform.
***Checked for relevance on 11-Dec-2013***

Goal


Why are Variances calculated for Co-Products (i.e, products which are not on the first line of the Batch) when using Standard Costing even when the profile option - GMF: Subledger Variance Type - is set to 'Scale to Actual' ?