Unable To Drill Down To The PO On expenditure items For Contignent Workers and unable to cost these items (Doc ID 1458367.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Costing - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

After importing contingent worker timercards to projects with purchasing integration (checked on the implementation options), the following happens :

 

     1) Despite the purchase order information is seeded on the assignment of the contingent worker, it is not possible to drill down on the expenditure Items to the option "Purchase Order Details"
There is the error : "You can select this option for PO related contingent work labor transactions only"

 

     2) Also, When running "PRC: Distribute Labor Costs" for the project  of the contingent worker, it is failing with the rejection reason code : NO_RATE "Missing Cost Rate"

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms