Setting Parameters To Ensure That Preventative Maintenance Work Orders Are Generated (Doc ID 1459735.1)

Last updated on MARCH 25, 2016

Applies to:

Oracle Enterprise Asset Management - Version 11.5.10.2 to 12.2.5 [Release 11.5 to 12.2]
Information in this document applies to any platform.
** Checked for relevance 24-Oct-2014 **

Symptoms

On : 12.0.5 version, The work orders can be forecasted and implemented using the Maintenance work bench (MWB), however the Generate Preventive Work orders concurrent program does not generate any work orders.


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Enterprise Asset Management -> Generate Work orders -> Enter the parameter such as date and Asset number
2.review the output

Cause