R12: Projects - Supplier Cost Interface Audit - The Item Date is not Within the Project Active Dates
(Doc ID 1525529.1)
Last updated on APRIL 04, 2025
Applies to:
Oracle Project Costing - Version 12.1.3 and laterInformation in this document applies to any platform.
Goal
After running PRC: Interface Supplier costs, the Supplier Cost Interface Audit shows the exception reason 'The item date is not within the project active dates.' The error is correct, but prior to R12.PJ_PJ.B.DELTA.5, the date could be changed in the Review Transactions form, where the date was typically corrected to the period of performance of the assigned project/task on the invoice line from Payables. Why are these exceptions not showing in the Review Transactions form?
Solution
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Goal |
Solution |