My Oracle Support Banner

Projects - Supplier Cost Interface Audit - The Item Date Is Not Within The Project Active Dates (Doc ID 1525529.1)

Last updated on OCTOBER 25, 2018

Applies to:

Oracle Project Costing - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

After running PRC: Interface Supplier costs, the Supplier Cost Interface Audit shows the exception reason 'The item date is not within the project active dates.'  The error is correct, but prior to R12.PJ_PJ.B.DELTA.5,  the date could be changed in the Review Transactions form, where the date was typically corrected to the period of performance of the assigned project/task on the invoice line from Payables.  Why are these exceptions not showing in the Review Transactions form?

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.