The Sugg Dock Date does not match the last resource requirement end date with Post Processing LT (Doc ID 1535930.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Process Manufacturing Process Planning - Version 12.1.3 and later
Oracle Advanced Supply Chain Planning - Version 12.1.3.8 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3.8 version, Memory Based Planner, integrated with Oracle Process Manufacturing (OPM)

ACTUAL BEHAVIOR
---------------
For some planned orders, when a post processing lead time is present for the made item through the Item Attribute Mass Maintenance, the Sugg Dock Date does not reflect the End Date of the last operation (resource requirement). This means that the resulting batch times will be incorrect. This is not the case for all planned orders.

EXPECTED BEHAVIOR
-----------------------
The Sugg Due Date and time to line up with the End Date and time of the last resource requirements consistently

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Set up post processing lead time for a make item
2. Run an ASCP Standard Collection,complete refresh
3. Run the ASCP constrained plan
4. Check the planned orders

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot release these planned orders back to OPM as the batches will be wrong

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms