Performance Measure At Completion Gives Wrong Totals For Financial Plans (Doc ID 1545960.1)

Last updated on AUGUST 01, 2016

Applies to:

Oracle Project Management - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

When setting up Performance Overview page to show the Performance Measure 'At Completion', the totals shown on the page for the budgets and forecasts are incorrect where the plan is not approved or primary.


Cause

Sign In with your My Oracle Support account