Issue With Planned Quantity In Workplan Resources (Doc ID 1547293.1)

Last updated on FEBRUARY 04, 2016

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Planned quantity entered is being reduced actuals entered on a task upon commit.

To reproduce:

Resource has completed 10hrs against a task.
Update planned amount to 100 hours.
When saving the planned quantity, application updates planned quantity to 90 hours.
The ETC should be 90, but the planned amount should remain as 100 hours.

As per documentation. ETC is planned amount less actuals. The planned amount should not be getting reduced.