Why Project Dates not equal to Dates from Template when Creating a Project from a Template by entering a Project Start Date different from Template? (Doc ID 1548526.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Foundation - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

Why the dates (also transaction control dates) differs from project template when creating a project from a template by entering a project start date different from template?

For example on a project template the effective from date for a transaction control is 04-Apr-2012 but when creating a project by copying from this template the effective from date for the same transaction control is 04-Apr-2013.

 

Solution