WICMLP - The WIP Mass Load Is Not Processing Records Found In The WIP_JOB_SCHEDULE_INTERFACE Table
(Doc ID 1550989.1)
Last updated on JULY 15, 2024
Applies to:
Oracle Work in Process - Version 12.1.3 to 12.2 [Release 12.1 to 12.2]Information in this document applies to any platform.
Symptoms
WICMLP - WIP Mass Load is not processing records from WIP_JOB_SCHEDULE_INTERFACE.
The records stay in the interface table with process_status of 2.
EXPECTED BEHAVIOR
WIP Jobs to be created
STEPS
The issue can be reproduced at will with the following steps:
1. Insert rows in the WIP_JOB_SCHEDULE_INTERFACE
2. WIP:Discrete: Run Import
3. One job is actually created but the Remaining jobs remain in PROCESS_STATUS = Running
Changes
The error message(s) exceeded 500 characters
Cause
To view full details, sign in with your My Oracle Support account. |
|