Can Raw Cost Of Capital Project Show In Expense Column Rather Than CIP OF Capital Project
(Doc ID 1555311.1)
Last updated on JULY 08, 2020
Applies to:
Oracle Project Costing - Version 12.1.2 and laterInformation in this document applies to any platform.
Goal
Qn1: How can we treat expenditures CIP costs as expenses and still keep the project as a capital projects
--Note: not using FA
Qn2: Can we keep tasks as capitalizable, and charge the cost as an expense in the capital project.
Have seen where the cost is in the expense Tab in Capital Project while the task is capitalized
-- How did this happen?
Solution