Goal

Qn1:How can we treat expenditures CIP costs as expenses and still keep the project as a capital projects
--Note: not using FA
 
Qn2:Can we keep tasks as capitalizable, and charge the cost as an expense in the capital project.
Have seen where the cost is in the expense Tab in Capital Project while the task is capitalized
-- How did this happen?
 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.