Changing Deliverable Status to Complete Gives This deliverable has deliverable actions with Billing function that has not been fully processed (Doc ID 1562828.1)

Last updated on JUNE 16, 2017

Applies to:

Oracle Project Billing - Version 12.1.3 and later
Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3, Deliverables

Attempt to change the status of the deliverable to ‘Completed’, the following error occurs:

This deliverable has deliverable actions with Billing function that has not been fully processed.
You need to process the billing event fully before completing the deliverable




Reproduction Steps

1. Create a new project
2. Create a deliverable
3. Create a billing action.
4. Go back to Deliverables and try to mark the deliverables status as completed along with a completion date

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms