For Cost Factors which do not have Payable Invoices, the Actual Cost = Estimated Cost; Estimated Charges are Getting Added In LCM Actual Cost Calculation (Doc ID 1563843.1)

Last updated on FEBRUARY 02, 2017

Applies to:

Oracle Landed Cost Management - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

Currently For Cost Factors which does not have Payable Invoices, the Actual Cost = Estimated Cost.

Example

-----------
cost factor- CSF charge
estimated cost from modifier - 100 KES
AP Invoices entered for this cost factor = null or not booked any payable invoices
Actual cost = 100 KES

User requirement is ACTUAL COST should be = 0 ,(not KES 100) since user has not booked any Payable Invoices for this Cost Factor.
 

Solution