Symptoms

Using Project Role and Named Person as resources in a Planning Resource List.
Creating workplan resource assignments using "Team role" resource. Then created PJR Team role (requirement) from this workplan role assignment (using Resource Usage page).
The Team role (requirement) got created under Resources tab from the workplan role assignment.
In PJR, assigned a resource  to the team role and approved by necessary approvers.
The assignment got confirmed after the approvals.
But this resulted with incorrect behavior in Workplan Task resource assignment:

At this point, the workplan task resource assigment got replaced by "PEOPLE" class resource. Previously it was "Project Manager" role.
Ideally it has to be replaced with Named Person "Leon Pretorius", which is the resouce been assigned to this role from PJR.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms