R12: Adding Project Level Resources Gives Error "Either bill rates, or conversion rates, or both are missing for some planning elements." (Doc ID 1576065.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Budgets setup as 'Cost and Revenue together' with separate resources
Error when resource added at the project level and costs entered.


ERROR:
  "Either bill rates, or conversion rates, or both are missing for some planning elements."

Cause