Symptoms

When sending progress from MSP to OP for a project where task percent roll up method is defined as quantity and task contains planned quantity and accumulated actual quantity, % complete is not calculated.

This is not an issue specific to the MSP integration, even while entering progress in Oracle Projects and changing value for "Actual Work Quantity to Date" and clicking on submit, the field "Physical Percent Complete" won't change.

Cause