Workplan Physical Percent Complete is not Updated (Doc ID 1585634.1)

Last updated on AUGUST 01, 2016

Applies to:

Oracle Project Management - Version 11.5.10.2 and later
Information in this document applies to any platform.

Symptoms

When sending progress from MSP to OP for a project where task percent roll up method is defined as quantity and task contains planned quantity and accumulated actual quantity, % complete is not calculated.

This is not an issue specific to the MSP integration, even while entering progress in Oracle Projects and changing value for "Actual Work Quantity to Date" and clicking on submit, the field "Physical Percent Complete" won't change.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms