My Oracle Support Banner

Alternate BOM/ Alternate Routing Is Not Selected For Some Planned Orders Of The Item In ASCP (Doc ID 1589722.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Process Manufacturing Process Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3.8 version, Install/Configuration

ACTUAL BEHAVIOR
---------------
One planned order of three having the same quantity and dates within the available date of the process effectivity has no alternate bom assigned and hence no resource requirements for that planned order or material requirements for the ingredients

EXPECTED BEHAVIOR
-----------------------

The alternate bom to be assigned

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Collect and constrained plan resulting in three planned orders for OPM Made items. Two have the alternate bom assigned one does not

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot rely on the results of planning

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.